Wates confirmed as Ardmore replacement on Hackney job
Summary
Hackney Council has appointed Wates to complete phase 2b of the Britannia Project after Ardmore Construction Group collapsed, leaving the residential scheme stalled. The new contract covers completion of the external envelope for four buildings, with practical completion now expected by the end of November 2027, around a year later than planned.
Why it matters
The case highlights the delivery and defect risks that can arise when a main contractor enters administration on a live residential scheme. Surveyors may see increased scrutiny of incomplete works, watertightness, certification gaps and potential claims linked to prior defective or uncertified work.
Key points
- Wates has been formally appointed to a £25.1m contract for phase 2b of the Britannia Project.
- The council says the priority is to complete the external envelope and make the buildings watertight.
- Hackney Council retains risks from Ardmore’s work, including likely spend on defects and testing uncertified works.
- Practical completion is now expected by the end of November 2027, about one year later than originally planned.
- A further JCT Prime Cost Building Contract 2024 for internal and landscape works is due for approval in spring 2027.