Gateway 3 approvals treble despite longer waits
Summary
The Building Safety Regulator has more than tripled Gateway 3 approvals in its latest reporting period, with 31 approvals issued over 12 weeks to 1 November. However, median approval times at Gateway 3 edged up to 21 weeks, while Gateway 2 decisions remained comparatively faster and covered 9,453 homes.
Why it matters
Gateway 3 is a critical control point for higher-risk buildings, particularly refurbishment and remediation schemes that may affect occupation and project sequencing. Surveyors working on relevant projects should note the regulator’s prioritisation approach, statutory check requirements and the continuing variability in determination times.
Key points
- Gateway 3 approvals rose to 31, up from nine in the previous report.
- Median Gateway 3 approval time increased slightly from 20 to 21 weeks.
- 11 Gateway 3 submissions were invalidated for failing initial statutory checks, including mandatory safety documentation.
- BSR said it is prioritising applications where occupation depends on approval.
- Gateway 2 approvals remained strong, with 40 of 42 applications approved covering 9,453 homes.
This is an RPSA summary of a publicly available article. The full content remains with the original publisher.