Health board has ‘no plans’ to sue Portakabin over delayed £11m ward
Summary
NHS Forth Valley says it is not currently planning legal action against Portakabin over delays to an £11m modular ward at Forth Valley Royal Hospital, despite having taken legal advice. The project remains unopened while the parties work through outstanding fire-safety compliance issues and develop a compliant fire strategy and remedial programme.
Why it matters
The case highlights how fire-safety compliance and approval processes can delay completion and occupation of modular healthcare buildings. For surveyors, it underlines the importance of robust design review, defect identification and evidence of compliance before handover or opening.
Key points
- The 30-bed modular ward remains unopened more than four years after construction began.
- Outstanding issues are mainly related to fire-safety compliance and smoke spread requirements.
- NHS Forth Valley is working with Falkirk Council, NHS Scotland Assure and the Building Standards Hub.
- Portakabin is developing a fire strategy and may carry out a bespoke fire and smoke test.
- A completion date will be set only after an acceptable fire-safety solution is agreed.