Grid delays hit £2bn Essex data centre
Summary
A planned £2bn data centre in Loughton, Essex, is likely to be delayed because grid power will not be available in time for the developer’s intended opening date. The article also highlights wider UK data centre delays caused by electricity connection constraints and notes an Ofgem-backed initiative to standardise connection designs.
Why it matters
Surveyors involved in industrial, infrastructure or strategic land projects may increasingly encounter viability and programme risks linked to grid capacity and utility connection lead times. The piece also signals growing demand for sites and buildings capable of supporting high-load energy infrastructure.
Key points
- Nscale’s planned 50MW data centre in Loughton is expected to be delayed due to power availability issues.
- The project may use gas fuel cells from Bloom Energy as an interim electricity solution.
- A consultancy report found grid connection delays are a major barrier for UK data centre developers.
- Ofgem has tasked United Infrastructure with developing standardised electricity connection archetypes for data centres.
This is an RPSA summary of a publicly available article. The full content remains with the original publisher.